[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898968,582,1,"单选题","在下列需签证的事件中，需要由发包人以书面形式向承包人发出指令的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","完成合同以外的零星项目",true,{"key":16,"text":17,"correct":18},"B","因场地条件导致合同工程内容不一致",false,{"key":20,"text":21,"correct":18},"C","因地质条件导致合同工程内容不一致",{"key":23,"text":24,"correct":18},"D","因水文条件导致合同工程内容不一致","承包人应发包人要求完成合同以外的零星项目、非承包人责任事件等工作的，发包人应及时以书面形式向承包人发出指令，提供所需的相关资料；承包人在收到指令后，应及时向发包人提出现场签证要求。2020教材P253-254",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]