[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898967,582,1,"单选题","某建设项目业主与施工单位签订了可调价格合同。合同中约定：主导施工机械一台为施工单位自有设备，台班单价900元／台班，折旧费为150元／台班，人工日工资单价为40元／工日，窝工工费10元／工日，以人工费为基数的综合费率为30％。合同履行中，因场外停电全场停工2天，造成人员窝工20个工日；因业主指令增加一项新工作，完成该工作需要5天时间，机械5台班，人工20个工日，材料费5500元，则施工单位可向业主提出索赔额为()元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11300",false,{"key":16,"text":17,"correct":18},"B","11540",true,{"key":20,"text":21,"correct":14},"C","13880",{"key":23,"text":24,"correct":14},"D","11600","此题所需要注意的是，窝工时台班单价按折旧费计算，且窝工时不能计取综合费用：则索赔额=2×150+20×10+(5×900+20×40+5500)+20×40×30％=11540(万元)。2020教材P245-253",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]