[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898966,582,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，中标人投标报价浮动率的计算公式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","（1-中标价\u002F招标控制价）×100%",true,{"key":16,"text":17,"correct":18},"B","（1-中标价\u002F施工图预算）×100%",false,{"key":20,"text":21,"correct":18},"C","（1-不含安全文明施工费的中标价\u002F不含安全施工费的招标控制价）×100%",{"key":23,"text":24,"correct":18},"D","（1-不含安全文明施工费的中标价\u002F不含安全施工费的施工图预算）×100%","2020版教材P238 ①实行招标的工程：承包人报价浮动率L=（1-中标价\u002F招标控制价）×100%②不实行招标的工程：承包人报价浮动率L=（1-报价值\u002F施工图预算）。上述公式中的中标价、招标控制价或报价值、施工图预算，均不含安全文明施工费。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]