[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898965,582,1,"单选题","关于施工过程中的现场签证，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人应按照现场签证内容计算价款，在竣工结算时一并支付",false,{"key":16,"text":17,"correct":14},"B","没有计日工单价的现场签证，按承包商提出的价格计算并支付",{"key":19,"text":20,"correct":14},"C","因发包人口头指令实施的现场签证事项，其发生的费用应由发包人承担",{"key":22,"text":23,"correct":24},"D","经发包人授权的工程造价咨询人，可与承包人做现场签证",true,"2020版教材P253 现场签证是指发包人或其授权现场代表（包括工程监理人、工程造价咨询人）与承包人或其授权现场代表就施工过程中涉及的责任事件所做的签认证明。施工合同履行期间出现现场签证事件的，发承包双方应调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]