[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898963,582,1,"单选题","因物价波动引起的价格调整，可采用价格指数法，在确定可调因子的现行价格指数时，所选择的日期是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","付款证书相关周期最后一天的前42天",true,{"key":16,"text":17,"correct":18},"B","竣工结算前42天",false,{"key":20,"text":21,"correct":18},"C","竣工验收前42天",{"key":23,"text":24,"correct":18},"D","竣工决算前42天","2020版教材P241 本题考查的是物价变化类合同价款调整事项。各可调因子的现行价格指数，指根据进度付款、竣工付款和最终结清等约定的付款证书相关周期最后一天的前42天的各可调因子的价格指数。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]