[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898960,582,1,"单选题","某施工现场有装载机2台，由施工企业租得，台班单价5000元／台班，租赁费为2000元／台班，人工工资为80元／工日，窝工补贴25元／工日，以人工费和机械费合计为计算基础的综合费率为30%。在施工过程中发生了如下事件：监理人对已经覆盖的隐蔽工程要求重新检查且检查结果合格，配合用工20工日，装载机4台班。为此，施工企业可向业主索赔的费用为（ ）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8080",false,{"key":16,"text":17,"correct":14},"B","9080",{"key":19,"text":20,"correct":14},"C","18080",{"key":22,"text":23,"correct":24},"D","28080",true,"2020版教材P247 本题考查的是工程索赔类合同价款调整事项。监理人对已经覆盖的隐蔽工程要求重新检查且检查结果合格，可以索赔工期、费用和利润。索赔金额=（20×80+4×5000）×（1+30%）=28080（元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]