[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898957,582,1,"单选题","因不可抗力原因造成的损失，应由承包人承担的情形是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因工程损害导致第三方人员伤亡",false,{"key":16,"text":17,"correct":14},"B","运至施工场地用于施工的工程设备的损害",{"key":19,"text":20,"correct":14},"C","工程所需修复费用",{"key":22,"text":23,"correct":24},"D","承包人的施工机械设备损坏",true,"2020版教材P245 本题考查的是工程索赔类合同价款调整事项。费用损失的承担原则：（1）合同工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工场地用于施工的材料和待安装的设备的损害，由发包人承担；（2）发包人、承包人人员伤亡由其所在单位负责，并承担相应费用；（3）承包人的施工机械设备损坏及停工损失，由承包人承担；（4）停工期间，承包人应发包人要求留在施工场地的必要的管理人员及保卫人员的费用由发包人承担；（5）工程所需清理、修复费用，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]