[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898948":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898948,582,1,"单选题","某工程项目合同价为2000万元，施工过程中收到外界的干扰使得工期拖延了20个月，该部分工程的合同价格为160万元，则承包商可提出的工期索赔为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.8个月",false,{"key":16,"text":17,"correct":18},"B","1.6个月",true,{"key":20,"text":21,"correct":14},"C","1.8个月",{"key":23,"text":24,"correct":14},"D","1.2个月","2020版教材P252 已知受干扰部分工程的延期时间，工期索赔值=受干扰部分工期拖延时间×（受干扰部分工程的合同价格\u002F原合同总价）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]