[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898944,582,1,"单选题","任一计日工项目实施结束后，下列费用计算说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程数量以承包人提交的现场签证报告为准，无须发包人确认",false,{"key":16,"text":17,"correct":18},"B","根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算",true,{"key":20,"text":21,"correct":14},"C","已标价工程量清单中没有该类计日工单价的，由发包人确定该类计日工单价",{"key":23,"text":24,"correct":14},"D","已标价工程量清单中没有该类计日工单价的，由承包人确定该类计日工单价","2020版教材P240 任一计日工项目实施结束。承包人应按照确认的计日工现场签证报告核实该类 项目的工程数量，并根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算， 提出应付价款；已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的有关的规定商定计日工单价计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]