[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898943,582,1,"单选题","某项目施工过程中发生工程变更，引起分部分项工程项目发生变化，已标价工程量清单中没有适用也没有类似于变更工程项目，调整该变更项目的单价应考虑报价浮动率。已知该工程的中标价为5030万元，招标控制价为5100万元，则承包人报价浮动率L为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.37％",true,{"key":16,"text":17,"correct":18},"B","1.39％",false,{"key":20,"text":21,"correct":18},"C","1.37",{"key":23,"text":24,"correct":18},"D","1.39","2020版教材P238 已标价工程量清单中没有适用也没有类似于变更工程项目的，由承包人根据变 更工程资料、计量规则和计价办法、工程造价管理机构发布的信息（参考）价格和承包人报价浮动率，提出变更工程项目的单价或总价，报发包人确认后调整。 实行招标的工程：承包人报价浮动率L=（1-中标价／招标控制价）×100％ 不实行招标的工程：承包人报价浮动率L=（1-报价值／施工预算值）×100％",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]