[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898938,582,1,"单选题","某施工合同在履行过程中，先后在不同时间发生了如下事件：因业主对隐蔽工程复检而导致某关键工作停工2天，隐蔽工程复检合格；因异常恶劣天气导致工程全面停工3天；因季节大雨导致工程全面停工4天。则承包人可索赔的工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","9","2020版教材P248 季节性大雨属于承包人可预料的事件，因此不能获得工期补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]