[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898936,582,1,"单选题","某工程项目总价值1000万元，合同工期12个月，现承包人因建设条件发生变化需增加额外工程费用100万元，则承包方可提出工期索赔为（ ）个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":14},"B","0.9",{"key":19,"text":20,"correct":21},"C","1.2",true,{"key":23,"text":24,"correct":14},"D","3.6","2020版教材P252 本题考查的是工程索赔类合同价款调整事项。工期索赔值=原合同总工期×额外增加的工程量的价格／原合同总价=12×100\u002F1000=1.2个月。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]