[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898923,582,1,"单选题","关于招标工程量清单缺项、漏项的处理，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单缺项、漏项及计算错误带来的风险由发承包双方共同承担",false,{"key":16,"text":17,"correct":18},"B","分部分项工程量清单漏项造成新增工程量的，应按变更事件的有关方法调整合同价款",true,{"key":20,"text":21,"correct":14},"C","分部分项工程量清单缺项引起措施项目发生变化的，应按与分部分项工程相同的方法进行调整",{"key":23,"text":24,"correct":14},"D","招标工程量清单中措施项目缺项，投标人在投标时未予以填报的，合同实施期间不予增加","2020版教材P239 施工合同履行期间，由于招标工程量清单中分部分项工程出现缺项漏项，造成新增工程清单项目的，应按照工程变更事件中关于分部分项工程费的调整方法，调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]