[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898920,582,1,"单选题","国际工程投标报价时，人工工日单价通常以工程用工量和国内（当地）工人完成工日所占比例进而加权得到的平均工资单价计算，通常权重可表示为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不同工人工日占总工日数百分比",false,{"key":16,"text":17,"correct":14},"B","不同工人工效占总工效百分比",{"key":19,"text":20,"correct":21},"C","不同工人工日占总工日数百分比／工效比",true,{"key":23,"text":24,"correct":14},"D","不同工人工效比／工日占总工日数百分比","2020版教材P232 （1）人工工日单价的计算。人工工日单价需根据工人来源情况确定。在国外承包工程，人工工日单价就是指国内派出工人和当地雇用工人的平均工资单价。这是以工程用工量和两种工人完成工日所占比例进而加权得到的平均工资单价。考虑工效的综合人工工日单价，其计算公式为：综合人工工日单价=国内派出工人人工工日单价X国内工人工日占总工日数百分比\u002F工效比+雇用当地工人人工工日单价X当地工人工日占总工日百分比\u002F工效比",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]