[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898919,582,1,"单选题","关于国际工程招标，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投交标书的方式须加以限制，如规定必须寄交某邮政信箱以免延误",false,{"key":16,"text":17,"correct":14},"B","开标时若标书未附投标保证金则拒绝开启",{"key":19,"text":20,"correct":14},"C","开标时允许投标人提问但不允许录音",{"key":22,"text":23,"correct":24},"D","采用“两个信封制度”的，技术上不符合要求的标书则第二个信封不再开启",true,"2020版教材P230 公开开标有变通办法，例如“两个信封制度”（Twoenve1opesystem），即要求投标书的技术性部分密封装入一个信封，而将报价装入另一个密封信封。第一次开标会时先开启技术性标书的信封；然后将各投标人的标书交评标委员会评比，视其是否在技术方面符合要求。第二次开标会时再将技术上符合要求的标书报价公开读出。技术上不符合要求的标书，其第二个信封不再开启。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]