[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898907,582,1,"单选题","根据《标准施工招标文件》（2007年版），关于“分包和偏离问题处理”的内容应包括于（ ）之中。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标公告",false,{"key":16,"text":17,"correct":18},"B","投标人须知",true,{"key":20,"text":21,"correct":14},"C","评标办法",{"key":23,"text":24,"correct":14},"D","合同条款与格式","2020版教材P223 1.工程总承包招标文件的编制内容（2）投标人须知。1）总则。主要包括项目概况，项目的资金来源和落实情况，招标范围、计划工期和质量标准，对投标人的资格要求，对费用承担和设计成果补偿、保密、语言文字、计量单位等方面的规定，对踏勘现场、投标预备会的要求，以及对分包和偏离问题的处理。 “分包和偏离问题的处理”是包含在总则内的，而总则是包含在投标人须知里面的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]