[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898896,582,1,"单选题","下列初步评审标准中属于响应性评审标准的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程进度计划与措施",false,{"key":16,"text":17,"correct":18},"B","投标报价校核",true,{"key":20,"text":21,"correct":14},"C","投标文件格式符合要求",{"key":23,"text":24,"correct":14},"D","联合体投标人已提交联合体协议书","响应性评审标准，主要的评审内容包括投标报价校核，审查全部报价数据计算的正确性，分析报价构成的合理性，并与招标控制价进行对比分析，还有工期、工程质量、投标有效期、投标保证金、权利义务、已标价工程量清单、技术标准和要求、分包计划等，均应符合招标文件的有关要求。2020教材P213-217",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]