[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898862":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898862,582,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，下列费用项目中需纳入分部分项工程项目综合单价的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程设备估价",true,{"key":16,"text":17,"correct":18},"B","专业工程暂估价",false,{"key":20,"text":21,"correct":18},"C","暂列金额",{"key":23,"text":24,"correct":18},"D","计日工费","2020版教材P201 综合单价包括完成一个规定清单项目所需的人工费、材料和工程设备费、施工机具使用费、企业管理费、利润，并考虑风险费用的分摊。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]