[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898858,582,1,"单选题","工程量清单计价模式下，确定分部分项工程单价的工作包括：①分析各清单项目的工程内容，②确定计算基础，③计算人工、材料、机械费用，④计算工程内容的工程量与清单单位含量，⑤计算综合单价。对上述工作先后顺序的排列，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②④⑤③",false,{"key":16,"text":17,"correct":18},"B","②①④③⑤",true,{"key":20,"text":21,"correct":14},"C","①②④③⑤",{"key":23,"text":24,"correct":14},"D","②①④⑤③","2020版教材P202 分部分项工程单价确定的步骤为：（1）确定计算基础；（2）分析每一清单项目的工程内容；最新题库，考前【黑钻押题】，金考典软件考前更新，下载链接 www.jinkaodian.com （3）计算工程内容的工程数量与清单单位的含量；（4）分部分项工程人工、材料、机械费用的计算；（5）计算综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]