[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898855":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898855,582,1,"单选题","关于招标控制价及其编制的说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价中包括应由招标人承担的风险费用",false,{"key":16,"text":17,"correct":14},"B","招标人供应的材料，总承包服务费应按材料价值的1．5％计算",{"key":19,"text":20,"correct":21},"C","措施项目费按招标文件中提供的措施项目清单确定",true,{"key":23,"text":24,"correct":14},"D","招标文件提供暂估价的主要材料，其主材费用应计入其他项目清单费用","综合单价中应包括招标文件中要求投标人所承担的风险内容及其范围(幅度)产生的风险费用，A选项错。 招标人自行供应材料的，总承包服务费按招标人供应材料价值的1％计算,B选项错。 措施项目应按招标文件中提供的措施项目清单确定，措施项目分为以“量”计算和以“项”计算两种。C选项正确。 对于未计价材料费〈包括暂估单价的材料费〉应计入综合单价，D选项错。2020教材P190-195",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]