[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898854,582,1,"单选题","在编制招标工程量清单过程中，拟定常规施工组织设计时，通常需要估算整体工程量的项目是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","抹灰",false,{"key":16,"text":17,"correct":14},"B","门窗",{"key":19,"text":20,"correct":21},"C","混凝土",true,{"key":23,"text":24,"correct":14},"D","梁板","在拟定常规的施工组织设计时需估算整体工程量。通常根据概算指标或类似工程进行估算，且仅对主要项目加以估算即可，如土石方、混凝土等。2020教材P184-190",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]