[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898849,582,1,"单选题","在编制脚手架工程量清单时，其工作内容不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","场内、场外材料搬运",false,{"key":16,"text":17,"correct":14},"B","安全网的铺设",{"key":19,"text":20,"correct":14},"C","选择附墙点与主体连接",{"key":22,"text":23,"correct":24},"D","测试手动装置、安全锁等",true,"2020版教材P189 例4.1.1计算脚手架工程量时，其工作内容包括：（1）场内、场外材料搬运；（2）搭、拆脚手架、斜道、上料平台；（3）安全网的铺设；（4）选择附墙点与主体连接；（5）测试电动装置、安全锁等；（6）拆除脚手架后材料的堆放。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]