[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898847,582,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，招标控制价的综合单价组价工作包括：①确定工、料、机单价；②确定所组价定额项目名称；③计算组价定额项目的合价；④除以工程量清单项目工程量；⑤计算组价定额项目工程量，下列工作排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②⑤①③④",true,{"key":16,"text":17,"correct":18},"B","①②⑤④③",false,{"key":20,"text":21,"correct":18},"C","②③①⑤④",{"key":23,"text":24,"correct":18},"D","①②③④⑤","2020版教材P194 首先，依据提供的工程量清单和施工图纸，按照工程所在地区颁发的计价定额的规定，确定所组价的定额项目名称，并计算出相应的工程量；其次，依据工程造价政策规定或工程造价信息确定其人工、材料、机具台班单价；同时，在考虑风险因素确定管理费率和利润率的基础上，按规定程序计算出所组价定额项目的合价",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]