[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898845":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898845,582,1,"单选题","下列关于投标人须知描述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在正文中的未尽事宜可以通过“投标人须知前附表”进行进一步明确",false,{"key":16,"text":17,"correct":14},"B","“投标人须知前附表”由招标人根据招标项目具体特点和实际需要编制和填写",{"key":19,"text":20,"correct":21},"C","“投标人须知前附表”无须与招标文件的其他章节相衔接",true,{"key":23,"text":24,"correct":14},"D","“投标人须知前附表”不得与投标人须知正文内容相抵触","2020版教材P183 C错：投标人须知，主要包括对于项目概况的介绍和招标过程的各种具体要求，在正文中的未尽事宜可以通过“投标人须知前附表”进行进一步明确，由招标人根据招标项目具体特点和实际需要编制和填写，但务必与招标文件的其他章节相衔接，并不得与投标人须知正文的内容相抵触，否则抵触内容无效。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]