[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898839,582,1,"单选题","招标人对已发出的招标文件进行的必要修改，应当在投标截止时间（ ）天前发出。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":14},"C","14",{"key":22,"text":23,"correct":24},"D","15",true,"2020版教材P184 招标文件的澄清将在规定的投标截止时间15天前以书面形式发给所有购买招标文件的投标人，但不指明澄清问题的来源。如果澄清发出的时间距投标截止时间不足15天，相应推迟投标截止时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]