[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898838,582,1,"单选题","下列内容中，属于招标工程量清单编制依据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程清单",false,{"key":16,"text":17,"correct":18},"B","拟定的招标文件",true,{"key":20,"text":21,"correct":14},"C","招标控制价",{"key":23,"text":24,"correct":14},"D","潜在投标人的潜质及能力","2020版教材P184 招标工程量清单编制的编制依据包括：（1）《建设工程工程量清单计价规范》GB 50500-2013以及各专业工程计量规范等；（2）国家或省级、行业建设主管部门颁发的计价定额和办法；（3）建设工程设计文件及相关资料；（4）与建设工程有关的标准、规范、技术资料；（5）拟定的招标文件；（6）施工现场情况、地勘水文资料、工程特点及常规施工方案；（7）其他相关资料。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]