[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898817":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898817,582,1,"单选题","采用工料单价法编制施工图预算，在套用定额预算单价时，若分项工程施工工艺条件与预算单价或单位估价表不一致而造成人工、机械的数量增减时，一般（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调量不调价",true,{"key":16,"text":17,"correct":18},"B","调价不调量",false,{"key":20,"text":21,"correct":18},"C","既不调价也不调量",{"key":23,"text":24,"correct":18},"D","既调价也调量","本题考查的是施工图预算的编制。分项工程施工工艺条件与预算单价或单位估价表不一致而造成人工、机具的数量增减时，一般调量不调价。2020教材P169-181",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]