[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898805,582,1,"单选题","某拟建工程初步设计已达到必要的深度，能够据此计算出扩大分项工程的工程量，则能较为准确地编制拟建工程概算的方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概算指标法",false,{"key":16,"text":17,"correct":14},"B","类似工程预算法",{"key":19,"text":20,"correct":21},"C","概算定额法",true,{"key":23,"text":24,"correct":14},"D","综合吨位指标法","本题考查的是设计概算的编制。运用概算定额法，要求初步设计必须达到一定深度，建筑结构尺寸比较明确，能按照初步设计的平面图、立面图、剖面图纸计算出楼地面 、墙身、门窗和屋面等扩大分项工程(或扩大结构构件)项目的工程量时，方可采用 。 2020教材P155-166",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]