[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898772,582,1,"单选题","当初步设计深度不够，设备清单不完备仅有成套设备重量时，编制单位工程概算宜采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扩大单价法",true,{"key":16,"text":17,"correct":18},"B","概算指标法",false,{"key":20,"text":21,"correct":18},"C","类似工程预算法",{"key":23,"text":24,"correct":18},"D","综合单价法","2020版教材P162 当初步设计深度不够，设备清单不完备，只有主体设备或仅有成套设备重量时，可采用主体设备、成套设备的综合扩大安装单价来编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]