[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898769,582,1,"单选题","关于设计概算的调整，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","若设计概算已通过批准，则不得调整",false,{"key":16,"text":17,"correct":14},"B","一个工程可多次调整设计概算",{"key":19,"text":20,"correct":21},"C","因项目建设期价格大幅上涨，可以向国家发展改期委员会申请调整概算",true,{"key":23,"text":24,"correct":14},"D","地质条件发生重大变化，不允许调整概算","2020版教材P148 设计概算经批准后，一般不得调整。 一个工程只允许调整一次概算。 因项目建设期价格大幅上涨，政策调整，地质条件发生重大变化和自然灾害等不可抗力因素等原因导致原概算不能满足工程实际需要的，可以向国家发展改期委员会申请调整概算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]