[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898730,582,1,"单选题","建设项目投资估算可以根据主体专业设计的阶段和深度采用混合法，下列方法中两两混合后属于混合法的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","生产能力指数法与系数估算法",false,{"key":16,"text":17,"correct":18},"B","系数估算法与比例估算法",true,{"key":20,"text":21,"correct":14},"C","单位生产能力估算法与比例估算法",{"key":23,"text":24,"correct":14},"D","系数估算法与单位生产能力估算法","2020版教材P135 混合法是根据主体专业设计的阶段和深度，投资估算编制者所掌握的国家及地区、行业或部门相关投资估算基础资料和数据，以及其他统计和积累的、可靠的相关造价基础资料，对一个拟建建设项目采用生产能力指数法与比例估算法或系数估算法与比例估算法混合估算其相关投资额的方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]