[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898706,582,1,"单选题","在计算预算定额人工消耗量时，基本用工中除包括完成定额计量单位的主要用工外，还应包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","劳动定额规定应增（减）计算的用工",true,{"key":16,"text":17,"correct":18},"B","劳动定额内不包括的材料加工用工",false,{"key":20,"text":21,"correct":18},"C","施工中不可避免的其他零星用工",{"key":23,"text":24,"correct":18},"D","质量检查和隐蔽工程验收用工","2020版教材P77 基本用工指完成一定计量单位的分项工程或结构构件的各项工作过程的施工任务所必需消耗的技术工种用工。基本用工包括：完成定额计量单位的主要用工；按劳动定额规定应增（减）计算的用工量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]