[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898702,582,1,"单选题","在正常施工条件下，完成10m3混凝土梁浇捣需4个基本用工，0.5个辅助用工，0.3个超运距用工，若人工幅度差系数为10%，则该梁混凝土浇捣预算定额人工消耗量为（ ）工日\u002F10m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.20",false,{"key":16,"text":17,"correct":14},"B","5.23",{"key":19,"text":20,"correct":14},"C","5.25",{"key":22,"text":23,"correct":24},"D","5.28",true,"2020版教材P77 预算定额人工消耗量=（4+0.3+0.5）×（1+10%）=5.28（工日\u002F10m3）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]