[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898682,582,1,"单选题","某挖掘机械挖二类土方的台班产量定额为100m3\u002F台班，当机械幅度差系数为20%时，该机械挖二类土方1000m3预算定期的台班耗用量应为（ ）台班。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8.0",false,{"key":16,"text":17,"correct":14},"B","10.0",{"key":19,"text":20,"correct":21},"C","12.0",true,{"key":23,"text":24,"correct":14},"D","12.5","2020版教材P79 施工机械台班时间定额=1\u002F100=0.01（台班\u002Fm3）预算定额机械耗用台班=0.01×（1+20%）=0.012（台班\u002Fm3）挖土方1000m3的预算定额机械耗用台班量=1000×0.012=12（台班）。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]