[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898673,582,1,"单选题","某施工机械配备司机2人，若年制度工作日为254天，年工作台班为250台班，人工单价为80元，则该施工机械的台班人工费为（ ）元\u002F台班。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","78.72",false,{"key":16,"text":17,"correct":14},"B","81.28",{"key":19,"text":20,"correct":14},"C","157.44",{"key":22,"text":23,"correct":24},"D","162.56",true,"2020版教材P73 台班人工费=2×[1+（254-250）\u002F250]×80=162.56（元\u002F台班）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]