[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898655,582,1,"单选题","下列（ ）是精度最高的写实记录法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","数示法",true,{"key":16,"text":17,"correct":18},"B","图示法",false,{"key":20,"text":21,"correct":18},"C","接续法",{"key":23,"text":24,"correct":18},"D","选择法","本题考查的是施工过程分解及工时研究。 写实记录法按记录时间的方法不同分为数示法、图示法和混合法三种，计时一般采用有秒针的普通计时表即可。数示法的特征是用数字记录工时消耗，是三种写实记录法中精确度较高的一种，精确度达5s。 选项C、D不属于写实记录法；数示法的精度高于图示法。2020教材P54-60",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]