[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898654,582,1,"单选题","以施工现场积累的分部分项工程使用材料数量、完成产品数量、完成工作原材料的剩余数量等统计资料为基础，经过整理分析，获得材料消耗数据的方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实验室试验法",false,{"key":16,"text":17,"correct":14},"B","现场技术测定法",{"key":19,"text":20,"correct":21},"C","现场统计法",true,{"key":23,"text":24,"correct":14},"D","理论计算法","本题考查的是确定材料定额消耗量的基本方法。现场统计法，是以施工现场积累的分部分项工程使用材料数量、完成产品数量、完成工作原材料的剩余数量等统计资料为基础，经过整理分析，获得材料消耗的数据。2020教材P64-65",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]