[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898650,582,1,"单选题","通过计时观察，完成某工程的基本工时为4h／m3，辅助工作时间为工序作业时间的8％。规范时间占工作时间的20％，则完成该工程的时间定额是（ ）工日／m3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.56",false,{"key":16,"text":17,"correct":14},"B","0.67",{"key":19,"text":20,"correct":21},"C","0.68",true,{"key":23,"text":24,"correct":14},"D","0.96","本题考查的是确定人工定额消耗量的基本方法。4h=0.5(工日／m3)；工序作业时间=0.5／(1-8％)=0.543；定额时间=0.543／(1-20％)=0.68(工日／m3)。 2020教材P61-63",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]