[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898647,582,1,"单选题","正常施工条件下，完成单位合格建筑产品所需某材料的不可避免损耗量为0.90kg。已知该材料的损耗率为7.20％，则其总消耗量为（ ）kg",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13.50",false,{"key":16,"text":17,"correct":18},"B","13.40",true,{"key":20,"text":21,"correct":14},"C","12.50",{"key":23,"text":24,"correct":14},"D","11.60","本题考查的是确定材料定额消耗量的基本方法。 总消耗量=0.9／7.2％+0.9=13.4(kg)。2020教材P64-65",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]