[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898646,582,1,"单选题","已知人工砌筑1m3标准砖墙的基本工作时间为4.5小时，辅助工作时间占工序作业时间的2％。准备与结束工作时间、不可避免的中断时间、休息时间分别占工作日的3％、2％、15％。则该人工砌筑1m3标准砖墙的时间定额是（ ）工日／m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.704",false,{"key":16,"text":17,"correct":18},"B","0.718",true,{"key":20,"text":21,"correct":14},"C","0.751",{"key":23,"text":24,"correct":14},"D","0.807","本题考查的是确定人工定额消耗量的基本方法。基本工作时间=4.5h=0.563(工日／m3)；工序作业时间=0.563／(1-2％)=0.574(工日／m3)；时间定额=0.574／(1-3％-2％-15％)=0.718(工日／m3)。2020教材P61-63",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]