[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898645,582,1,"单选题","在必需消耗的时间中，有一类时间与工作量大小无关，而往往和工作内容相关，这一时间应是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","准备与结束工作时间",true,{"key":16,"text":17,"correct":18},"B","基本工作时间",false,{"key":20,"text":21,"correct":18},"C","休息时间",{"key":23,"text":24,"correct":18},"D","辅助工作时间","本题考查的是施工过程分解及工时研究。准备和结束工作时间的长短与所担负的工作量大小无关，但往往和工作内容有关。2020教材P54-60 考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]