[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898644,582,1,"单选题","下列施工机械消耗时间中，属于机械必需消耗时间的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","未及时供料引起的机械停工时间",false,{"key":16,"text":17,"correct":14},"B","由于气候条件引起的机械停工时间",{"key":19,"text":20,"correct":14},"C","装料不足时的机械运转时间",{"key":22,"text":23,"correct":24},"D","因机械保养而中断使用的时间",true,"2020版教材P57页 本题考查的是机械必需消耗时间的内容。 在必需消耗的工作时间里，包括有效工作、不可避免的无负荷工作和不可避免的中断三项时间消耗。 不可避免的中断时间是与工艺过程的特点、机器的使用和保养、工人休息有关的终端时间。ABC均属于损失的工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]