[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898640,582,1,"单选题","通过计时观察，完成某工程的基本工时为6h\u002F㎡，辅助工作时间为工序作业时间的8%。规范时间占工作时间的15%，则完成该工程的时间定额是（ ）工日／㎡。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.93",false,{"key":16,"text":17,"correct":14},"B","0.94",{"key":19,"text":20,"correct":14},"C","0.95",{"key":22,"text":23,"correct":24},"D","0.96",true,"2020版教材P63 本题考查的是时间定额的计算。 工序作业时间=基本工作时间+辅助工作时间=基本工作时间\u002F（1-辅助时间%）（2.3.5）；定额时间=工序作业时间\u002F（1-规范时间%）（2.3.6）；因此基本工作时间=6h=0.75工日／㎡,工序作业时间=0.75\u002F（1-8%）=0.82工日\u002F㎡,时间定额=0.82\u002F（1-15%）=0.96工日／㎡",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]