[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898638,582,1,"单选题","确定材料消耗量时，现场技术测定法主要用来测定材料（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","消耗量定额",false,{"key":16,"text":17,"correct":18},"B","损耗定额",true,{"key":20,"text":21,"correct":14},"C","净用量定额",{"key":23,"text":24,"correct":14},"D","必需消耗量","2020版教材P64 材料消耗量定额由两个部分组成，即净用量定额和损耗定额。确定方法主要有现场技术测定法、实验室试验法、现场统计法和理论计算法。由于材料净用量可以通过理论计算和实验室试验方法编制，因此现场技术测定主要用来计算材料的损耗定额。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]