[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898634,582,1,"单选题","根据施工过程工时研究结果，与工人所担负的工作量大小无关的必须消耗时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基本工作时间",false,{"key":16,"text":17,"correct":14},"B","辅助工作时间",{"key":19,"text":20,"correct":21},"C","准备与结束工作时间",true,{"key":23,"text":24,"correct":14},"D","多余工作时间","2020版教材P56 准备与结束工作时间是执行任务前或任务完成后所消耗的工作时间。如工作地点、劳动工具和劳动对象的准备工作时间，工作结束后的整理工作时间等。准备和结束工作时间的长短与所担负的工作量大小无关，但往往和工作内容有关。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]