[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898628,582,1,"单选题","根据计时观察法测定某人工挖基坑二类土1m3的有关数据如下：基本工作时间180min，辅助工作时间占工序作业时间的百分比为10%，规范时间占工作日时间百分比为20%，则挖该基坑1m3的定额时间为（ ）min。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","243.0",false,{"key":16,"text":17,"correct":14},"B","247.5",{"key":19,"text":20,"correct":21},"C","250.0",true,{"key":23,"text":24,"correct":14},"D","257.1","2020版教材P63 按照人工定额消耗量的构成，应先计算该工序作业时间，再计算定额时间。 工序作业时间=基本工作时间／（1-辅助工作时间%）=180／（1-10%）=200（min／m3） 定额时间=工序作业时间／（1-规范时间%）=200／（1-20%）=250（min／m3）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]