[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898623,582,1,"单选题","在工人工作时间分类中，由于材料供应不及时引起工作班内的工时损失应列入（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工本身造成的停工时间",true,{"key":16,"text":17,"correct":18},"B","非施工本身造成的停工时间",false,{"key":20,"text":21,"correct":18},"C","准备与结束工作时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间","2020版教材P57 施工本身造成的停工时间，是由于施工组织不善、材料供应不及时、工作面准备工作做得不好、工作地点组织不良等情况引起的停工时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]