[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898608,582,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500--2013的规定，为合同约定调整因素出现时进行工程价款调整而预备的费用，应列入（ ）之中。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":18},"B","暂估价",false,{"key":20,"text":21,"correct":18},"C","计日工",{"key":23,"text":24,"correct":18},"D","措施项目费","本题考查的是其他项目清单。暂列金额是指招标人在工程量清单中暂定并包括在合同价款中的一笔款项。用于工程合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的合同价款调整，以及发生的索赔、现场签证确认等的费用。2020教材P48-51",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]