[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898603,582,1,"单选题","分部分项工程量清单是指表示拟建工程分项实体工程项目名称和相应数量的明细清单，应包括的要件是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目编码、项目名称、计量单位和工程量",false,{"key":16,"text":17,"correct":14},"B","项目编码、项目名称、项目特征和工程量",{"key":19,"text":20,"correct":14},"C","项目编码、项目名称、项目特征、计量单位和工程单价",{"key":22,"text":23,"correct":24},"D","项目编码、项目名称、项目特征、计量单位和工程量",true,"本题考查的是分部分项工程项目清单。分部分项工程量清单应包括项目编码、项目名称、项目特征、计量单位和工程量。2020教材P44-47",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]