[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898595,582,1,"单选题","招标工程清单编制时，在总承包服务费计价表中，应由招标人填写的内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","服务内容",true,{"key":16,"text":17,"correct":18},"B","项目价值",false,{"key":20,"text":21,"correct":18},"C","费率",{"key":23,"text":24,"correct":18},"D","金额","2020版教材P51 总承包服务费计价表的编制，项目名称、服务内容由招标人填写，编制招标控制价时，费率及金额由招标人按有关计价规定确定；投标时，费率及金额由投标人自主报价，计入投标总价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]